Corilis Digital Infrastructure Limited, the FTSE 250 owner of communications towers, data centres and fibre networks across Europe and North America, has reported portfolio revenue of £212.9 million for the six months ended 30 September 2026, an 18.1% rise on a constant-currency basis. Portfolio EBITDA reached £87.3 million, up 3.5%, with margin growth partly diluted by the lower-margin connectivity business acquired from BT Ireland. NAV per share closed the period at 145.8p, up from 143.7p on an ex-dividend basis, delivering a NAV total return of 1.4% after a £31.2 million foreign exchange headwind from sterling strength.
The company, which rebranded from Cordiant Digital Infrastructure in November 2026 following executive chairman Steven Marshall's acquisition of the investment management vehicle, declared a first interim dividend of 2.225p per share, payable on 22 December 2026. AFFO covers the dividend 1.8 times before scheduled debt repayments and 1.6 times after. Gearing stands at 40.2% of gross asset value, with 75% of drawn debt fixed or hedged.
AI demand converts into contracts
Revenue directly attributable to AI workloads remains under 1% of the portfolio total, but the company says new contracts demonstrate accelerating momentum. Czech platform CRA has signed GPU-as-a-service agreements with seven customers covering 29 nodes and generating approximately £7.1 million of annualised contracted revenue. The service runs on NVIDIA B300 GPUs from CRA's DC Lužice facility, which is being expanded from 200kW to up to 900kW by mid-2027. CRA has committed around £26.8 million to GPU purchases to date, with a further 40 nodes ordered in October 2026.
Construction of Prague Gateway, CRA's flagship new-build data centre on the edge of the Czech capital, began in September 2026. Letters of intent from AI providers, sovereign cloud operators, enterprises and governments now exceed 45MW. CRA is leading the Czech bid for a 50MW EU AI Gigafactory slot, with awards expected next year. The site holds 50MW of secured utility power from two separate grid connections and targets a PUE of 1.25. Phase one will cost up to CZK 2.1 billion (£75 million); a full three-module build is estimated at a minimum of £139 million. In Belgium, Datacenter United signed a 3MW high-density contract at its Machelen facility, with billing commencing April 2027.
Market context and competitive positioning
Corilis sits within a rapidly consolidating European digital infrastructure market in which secured grid power has become the primary constraint on new data centre capacity. The company's deliberate focus on smaller national markets, notably the Czech Republic, Poland and Belgium, positions it away from the land and power scarcity that characterises Paris, Frankfurt and Amsterdam. This strategy is increasingly endorsed by data-sovereignty policy across the EU, which is directing compute demand toward in-country facilities.
The EU AI Gigafactory programme, backed by up to €10 billion of public funding with the aim of catalysing more than €20 billion of private investment, represents a material potential anchor for Prague Gateway. No value from the bid is included in current valuations. Competitors for the CEE slot are not named in the release, but the Czech colocation market holds only around 50MW of live capacity nationally, a fraction of the major Western European hubs, giving Prague Gateway a structural advantage that would be difficult for a new entrant to replicate given multi-year grid connection timelines.
Hudson, the company's New York interconnect data centre, is on course for run-rate EBITDA breakeven next financial year after signing contracts totalling 2.6MW. A customer filing for bankruptcy impacted near-term revenue recognition but the company says the space will be re-leased. Shares traded at an 18.7% discount to NAV at 20 November 2026; the board says the discount reflects wider UK listed-market conditions rather than portfolio performance.
The board is evaluating funding options for a pipeline of costed growth opportunities totalling at least £400 million across all sub-sectors, with double-digit return potential cited across committed projects. Minority co-investment is being explored for the first phase of Prague Gateway.